• The KSR project will be achieved in a period of 2 years starting from 2018 and being launched in 2021. Following are the major milestones of the plan

  • Phase 1

    (2018-2019)

    Workshop Setup

    Completed

    KSR-1 Engine Fabrication & Testing

    Ongoing

    Recovery System Design & Testing

    Ongoing

    Launch Rail Preparation

    Pending

    KSR-1 Test Vehicle 10km Launch

    Pending

  • Phase 2

    (2020-2021)

    KSR-2 Engine Fabrication & Testing

    Pending

    KSR-2 Suborbital 100km Launch

    Pending